Current Design and Construction Projects
2023 Asphalt Repairs and New Installations
- Estimated Start – June 2023
- Estimated Completion – August 2023
Henderson Gymnasium Locker Room Renovation
- Start – May 2023
- Estimated Completion – August 2023
Carpet and Paint at Naugle Hall
- Start – June 2023
- Estimated Completion – August 2023
Old Main Visitor Center Improvements
- Start – May 2023
- Estimated Completion – December 2023
Concrete Sidewalk and Stair Repairs
- Start – June 2023
- Estimated Completion – August 2023
Grove Forum Renovation
- Estimated Start – July 2023
- Estimated Completion – October 2023
Franklin Science Renovation Design
- Start – April 2022
- Estimated Completion – March 2024
MCT Computer Room AC Replacement
- Estimated Start – May 2024
- Estimated Completion – June 2024
Little Red School House Restoration
- Estimated Completion – June 2022